ARISS Scheduling Update

An urgent EVA to repair a broken power module on the ISS was performed on 2019-10-18. This work has caused the ARISS schedule to be moved back and is currently in flux. At this time the LARG ARISS team doesn’t know when the new window will be. Although based on orbital predictions it should be in the morning between 9a and 12p.

Setup is still targeted for the week of 2019-10-21.


Date StartEndDescription
2019-10-223:30pBefore 9pMove Hardware To School
2019-10-233:30pBefore 9pMove Antenna To Roof
&
Setup
2019-10-24TBD3:30pAny Pre-Rehearsal Setup
2019-10-243:30p5pDress Rehearsal
TBDTBDTBDISS Contact Day